All processes
PRC.39 · Construction Process

Precast Concrete: Production and Erection

On site, concrete is born once, under whatever weather the day brings, and cannot be inspected until it is too late. In the factory it is born a thousand times identical, under cover, and every unit can be looked at before it is erected. The price of that gain is exact: everything that is born continuous in cast in-situ work becomes, here, a joint.

Factory tolerance
in the order of a few millimetres
Erection tolerance
in the order of a centimetre
Demoulding
well before 28 days
Reuses of a steel mould
hundreds of cycles

Overview

TAV. 00

Prefabrication means moving production from the place where the work will stand to the place where it can be controlled. The advantage is not only speed: concrete cures at governed temperature and humidity, the moulds are steel and reused hundreds of times, and every element leaves with a repeatable geometry and a surface that would be hard to achieve in situ. In exchange, the building stops being a single body and becomes a set of pieces, and that shifts the centre of gravity of the design in two ways worth holding in mind from the outset. The first is that the pieces must be able to travel: maximum size is not decided by structural analysis, it is decided by the road and the crane. The second, and more important, is that the building's behaviour depends entirely on the joints, that is, on zones that simply do not exist in a cast in-situ structure. And it is in the joint that the genuinely demanding part of this process concentrates, because that is where precast earned its bad reputation when it was done badly, and its better reputation when it was done well.

The site score

TAV. H
NOT TO SCALE0 of 5 layers in place

The detail of the craftthe unit inside the transport envelope

SAGOMA LIMITE DI TRASPORTOPANNELLO PREFABBRICATOmargine, non optionalancoraggi di sollevamento
01Weeks 1-4

Designing in parts: dividing the building into pieces that can travel

The building is broken down into elements, the joint positions are decided, and each piece is checked as transportable and liftable. Anchor points, production and erection tolerances are defined, along with the sequence in which the pieces will arrive, because the delivery order is as much part of the design as the geometry.

Why it is done this wayIn cast in-situ construction the size of the elements is decided by structural analysis; in precast it is decided by the road, the bridge to pass under and the crane radius, and these are constraints that admit no negotiation once work has started. But the most delicate point of this phase is not dimensional, it is conceptual: deciding where a joint falls means deciding where the structure will be discontinuous, and therefore where the continuity that in-situ casting gave away for free will have to be rebuilt. A joint placed in the middle of a heavily stressed zone forces a complicated, expensive detail for the rest of the building's life; the same joint moved two metres, where stresses are modest, becomes a simple detail. This choice is made on the drawing and costs nothing; making it again later costs as much as remaking the moulds.
sagoma · transport envelope before an abnormal load is required2 tolleranze · one for production and one for erection, and they differ
In handthree-dimensional model of the elementserection plan and delivery schedule
the delivery sequence is design, not logistics
The mistake that costs dearlyDrawing the units and only then checking transport: you discover during production that two elements in ten will not pass, and you redesign once the moulds have already been made.
Site supervision checkVerify that the joint design is consistent with the declared structural scheme and that an erection plan exists with the sequence and temporary stability measures; check the declared tolerances both from the producer and from any existing concrete works.
«The maximum size of a unit does not come from the calculation: it comes from the road and the crane. And those you cannot talk round.»site notebook — editorial synthesis
The beats — with site daysbeat 1 of 5
12-24 hthe unit is demoulded once it has the strength to survive its own lifting, which comes well before final strength but does not come immediately

click a beat · arrow keys ← → walk the site · dashed pauses are the chemistry at work

The conditions nobody sees

A precast unit lives its hardest life before it is ever erected

TAV. G1

In the usual way of thinking, a structure is checked for the loads it will carry when finished. For a precast element that is true only of the last of its conditions, and often not even the most severe. The same panel passes through four completely different structural schemes within a few days: it lies flat in the mould, it is lifted from two or four points while its strength is still partial, it travels absorbing the accelerations of the road, and only at the end does it start working as it was conceived. Cracks found on precast almost always originate in one of the first three conditions, which is why they bear no relation to service loads: they are the signature of a moment when the unit was handled according to a scheme nobody had checked it for.

1 · NEL CASSEROappoggio continuo2 · SOLLEVAMENTOresistenza ancora parziale3 · TRASPORTOaccelerazioni della strada4 · IN OPERAlo schema previstola condizione critica è quasi sempre la seconda o la terza, mai la quartaed è per questo che i ganci di sollevamento non sono un suggerimento

A qualitative diagram of the transient conditions; lifting, transport and storage checks are part of the element design and are the producer's responsibility, but they must be asked for and read.

Where everything is decided

The joint does not connect the units: it defines what structure they are

TAV. G2

Looking at a finished precast building you cannot tell which connection logic was chosen, and yet it is the decision that governs its behaviour. A simple bearing transmits compression only: it is quick, cheap and tolerant of imprecision, but it produces a set of pieces that under horizontal actions must be held together by something else. A bolted or welded mechanical connection also transmits tension and is effective immediately, but it concentrates forces at a few points that become critical. An in-fill pour with lapped reinforcement is the slowest and most demanding on site, but it is also the only one that genuinely rebuilds, at the node, something close to monolithic behaviour. The choice is not a detailing preference: it is the definition of the building's structural scheme, and in a seismic area it is the single most important decision of the whole design.

APPOGGIOsolo compressioneserve altro per il sismaMECCANICOtrasmette trazione subitoconcentra in pochi puntiGETTO INTEGRATIVOricostruisce il nodoma chiede tempo e curain zona sismica questa non è una scelta di dettaglio: è il progetto

A qualitative comparison of the three logics; the choice and its verification belong to the structural engineer, and in a seismic area the capacity of the connections is the central design theme, not a detailing matter.

How it ages (and what betrays it)

TAV. P
FESSURE DA MOVIMENTAZIONECracks matching no service load pattern: they originate in lifting, transport or storage on the wrong supports (phase 03). They often stay invisible until they start letting water through, years later.
TOLLERANZE CUMULATEJoints come out too wide or too narrow and the units do not meet: the design sized the joints on factory tolerance while ignoring the foundation and erection ones (phase 04). It comes to light halfway through erection, when correction is enormously expensive.
NODO NON SOLIDARIZZATOIn-fill pour not compacted or reinforcement laps insufficient (phase 05): the structure behaves as a set of resting pieces rather than the frame intended, and the difference emerges only under horizontal action.
PONTE TERMICO AL CONNETTORECold bands and condensation marks along the connectors and the joints between sandwich panels (phase 02): the insulation is continuous everywhere except where something crosses it, and that something is nearly always metal.
GIUNTO DI FACCIATA APERTOWater penetration along the vertical lines between panels: watertightness left to a face-applied sealant alone, which ages in the sun and tears when the units move (phase 05). It is the historic defect of precast facades.

Questions from the site

TAV. Q
Does precast inevitably mean anonymous?

No, and the confusion is historical rather than technical. The bad reputation comes from a period when prefabrication meant repeating the same unit as often as possible, because almost all the cost sat in the mould: few moulds, many identical buildings. That economic logic has changed. With numerically controlled cutting and adaptable moulds, dimensional variation costs far less than it did, and variety can also be achieved without changing the mould at all, by working the surface: matrices that imprint texture, exposed aggregate obtained with retarders, pigments through the mass, blasting and treatments that would be impossible or ruinously expensive in situ. There is in fact a reversal that is rarely told: genuinely successful fair-faced concrete is much easier to obtain in a factory than on site, because there the mould is steel, the pour is controlled and the unit is rejected if it is not good. In situ, a botched fair-faced pour simply stays there.

How does a precast building behave in an earthquake?

It depends almost entirely on the connections, which is why the question has no single answer. A precast building with simply seated units can have perfectly sound elements and still behave badly, because under horizontal action the pieces tend to move relative to one another and the structure has no continuity through which to redistribute forces. A building with nodes able to transmit tension and moment behaves comparably to one cast in situ. The historically critical point, which has produced serious damage in real events, is precisely the seating of beams and roof units left to friction or to connections conceived only for vertical loads: when horizontal action exceeds friction, the element slides, and if the seating length runs out it falls. Two practical implications follow: on existing buildings, the connections are the first thing to check in a vulnerability assessment; on new ones, node capacity must be explicitly required and never assumed just because the element is certified.

Who governs the tolerances, and why are they such a frequent problem?

The problem arises because tolerances belong to different parties who do not talk to each other. The producer works to very high precision, in the order of millimetres, because the mould is steel and repeatable. The structure receiving the units, typically foundations or in-situ works, has precision an order of magnitude coarser, because it was made by other means and other logics. Erection adds a third. The joint is the only place where these three imprecisions meet, and it must absorb all of them together in the worst case, not in the average case. The recurring error is designing the joint from the producer's data sheet, which quotes the smallest of the three tolerances. The practical countermeasure is equally simple: survey the existing works before sending the units into production, not after, because it is the only moment when a discrepancy is corrected by changing a drawing rather than by demolishing something.

Can precasting be done with low-footprint concretes?

Precasting is in fact the setting where these materials work best, and the point is worth grasping because it is counter-intuitive. Concretes with recycled aggregate and those with alternative binders, such as geopolymers, all share the same practical problem: they are more sensitive to curing conditions and more variable, so on site they add uncertainty to a process that already has too much. In a factory that sensitivity stops being a defect, because curing is controlled, the mix is consistent batch by batch and every unit can be tested before it leaves. Some alternative binders in particular perform best precisely with the heat curing that is already standard practice in a plant. Two conditions remain unavoidable. The first is consistency of recycled aggregate supply, because a heterogeneous material produces inconsistent units. The second concerns fair faces: recycled aggregates bring colour variation that shows on a facade, so either that variability is accepted as a character, or the recycled content goes into the load-bearing wythe and not the outer one.

Materials involved

TAV. M