Skip to main content
ARCHITHECA.
Compliance NavigatorBetaTime MachineBetaSpecification CheckerBetaBlueprintComing soonState ExamBeta
MaterialsBuilding systems
RegulationsConstruction processesLexiconThe network
Journal
ARCHITHECA.
TOOLS
BlueprintCompliance NavigatorTime MachineSpecification CheckerState Exam
MATTER
MaterialsBuilding systems
KNOWLEDGE
RegulationsConstruction processesLexiconThe networkJournal

Newsletter

The journal, now and then.

New pieces, materials and notes from the field. No spam, unsubscribe anytime.

By subscribing you accept the Privacy Policy.

ARCHITHECA.

Material library and journal of architecture, building technique and design culture.

Explore

HomeJournalBlueprintMaterialsBuilding systemsSearch

Knowledge

RegulationsConstruction processesLexiconThe networkGeneral indexState Exam

Info

Method & AboutPropose a themePrivacy & LegalContact

© 2026 Architheca — All rights reserved

Independent editorial project
← All systems
Technical sheet
A.01A.02
SystemS-31

Isolated footing foundation

The simplest shallow foundation: under each column a footing, a widened block of reinforced concrete that takes the concentrated load and spreads it onto the soil over a larger area, lowering the pressure to values the ground can bear. It is cheap and quick when the soil is good and loads are moderate; the footings are then tied with beams (ground beams) to stiffen them and distribute the horizontal actions.

FondazioniShallow point foundation
B.01
System build-up6 layers
PILASTROreazione del terreno1. Pilastro2. Plinto in c.a.3. Ferri del pilastro4. Armatura inferiore5. Magrone6. Reazione terreno

Technical section of the system, from inside (left) to outside (right).

Shallow point foundation
Lato del plinto (pianta)
100-300cm
Altezza del plinto
40-100cm
Classe del calcestruzzo
≥ C25/30
Copriferro verso terra
≥ 4-5cm
Magrone di pulizia
≥ 10cm
Pressione sul terreno
150-350kPa
Descriptive memo

The simplest shallow foundation: under each column a footing, a widened block of reinforced concrete that takes the concentrated load and spreads it onto the soil over a larger area, lowering the pressure to values the ground can bear. It is cheap and quick when the soil is good and loads are moderate; the footings are then tied with beams (ground beams) to stiffen them and distribute the horizontal actions.

The isolated footing is the most direct way to found: each column sheds onto its own block of reinforced concrete, widened downward, that bears on the soil. It is the «point» shallow foundation, the cheapest when the soil is strong and uniform and the loads are moderate. Where the ground worsens or the loads grow, one moves to inverted beams or a raft.

Widen to lower the pressure

The principle is elementary: the column concentrates a large force on a small section; the footing gathers it and spreads it onto a wider base. The wider the base, the lower the pressure on the soil (force divided by area). The plan size of the footing is calculated exactly so: just wide enough for the pressure to stay below the allowable bearing capacity of the soil.

How it works: the inverted cantilever

Under the load, the soil reaction pushes the footing up at the edges, which behave as cantilevers fixed into the central stub: they tend to bend and crack at the bottom. This is why the main mesh reinforcement sits at the bottom, near the soil; and punching must be checked, because the column tends to «punch» through the footing with a cone-shaped failure.

Ties and details

Single footings are independent points: to keep them from settling or moving each on its own — especially in seismic areas — they are tied with ground beams that stiffen them and distribute the horizontal actions. Beneath, a blinding layer gives a level casting base; the cover toward the soil protects the reinforcement. Where the column is eccentric (on a boundary), the footing is combined with a beam to prevent overturning.

At a glance

Composition

6 layers · 3 materials · 1 processes

Strengths

  • The simplest, cheapest foundation on good soil
  • Localised digs and pours: fast and little material
  • Spreads the load, lowering the pressure
  • Tieable with ground beams for seismic action

Execution specs

Footing side (plan)
100–300 cm
Footing depth
40–100 cm
Concrete class
≥ C25/30
Cover toward the soil
≥ 4–5 cm
Soil pressure
150–350 kPa

Normative references

D.M. 17/01/2018 — NTCUNI EN 1997 (Eurocodice 7)UNI EN 1992 (Eurocodice 2)UNI EN 1998 (Eurocodice 8, sisma)UNI EN 206 (calcestruzzo)D.P.R. 380/2001
Systems architecture

Why it works

Widen the base · inverted cantilever
loadpunching conelow, uniform pressureinverted cantilever: the soil bends the edges up→ tension reinforcement at the bottom

The footing does two things. It widens the base: by spreading the column load over a larger area, it lowers the pressure on the soil to a bearable value (force divided by area). And it behaves as an inverted cantilever: the soil reaction, from below, bends the footing edges upward, so they tend to crack at the bottom — this is why the tension reinforcement sits at the bottom, near the soil. Punching remains to be checked, because the column tends to «punch» through the footing with a cone-shaped failure.

Material and effort by foundation type

Comparison · insulants
Isolated footings
minimum
Inverted beams
medium
Raft
high
Piles
maximum

Shorter bar = less material and simpler to build. On good, uniform soil with moderate loads, isolated footings are the most economical and direct foundation; piles are the heaviest commitment.

Nodal details

Critical junctions · sections
123456
D.01
Column–footing node

The column bars are anchored into the footing with starter bars; the main mesh sits at the bottom, in tension, and a punching check governs the depth so the column does not punch a cone through the pad.

  1. Column
  2. R.C. footing
  3. Column / starter bars
  4. Bottom reinforcement (mesh)
  5. Punching cone
  6. Blinding layer
123456
D.02
Ground beam (tie)

Ground beams tie adjacent footings into a frame: they stiffen them, carry the differential settlements and, above all, distribute the horizontal seismic actions so the footings do not move each on its own.

  1. Footing
  2. Column
  3. Ground beam (tie)
  4. Tie-beam reinforcement
  5. Blinding / soil
  6. Tied footing

Installation controls

Specification · checklist

01 · Excavation & base

Bearing soil as in the report
Excavation levels and plan size
Compacted, clean bottom

02 · Blinding & waterproofing

Blinding layer cast level
Waterproofing where groundwater
Water-stops at the joints

03 · Reinforcement & starters

Bottom mesh, cover spacers
Column starter bars anchored
Shear reinforcement if needed

04 · Pour & cover

Concrete class and slump
Cover toward the soil guaranteed
Vibration, no segregation

05 · Tie beams & backfill

Ground beams between footings
Curing of the cast
Backfill in compacted layers

Recurring defects

Diagnostics · site
Meccanica
Differential settlement between footings
CauseOn a non-uniform or poorly investigated soil, single footings settle by different amounts; without tie beams the structure follows and cracks.
PreventionGeotechnical investigation, footings sized to the pressure, ground beams, joints between blocks of different load.
Meccanica
Punching cracking of the footing
CauseA footing too shallow for the column load: the column tends to punch a cone through the pad, with cracks around the column.
PreventionDepth from the punching check, shear reinforcement if needed, correct column position.
Termo-igrometrica
Corrosion of the reinforcement
CauseInsufficient cover toward the soil and aggressive groundwater corrode the bottom mesh and crack the concrete.
PreventionCover ≥ 4–5 cm, blinding layer, exposure-class concrete, sulphate-resisting cement where needed.
Termo-igrometrica
Groundwater pressure and infiltration
CauseBelow the water table, uplift and infiltration stress and wet the footing if it is not waterproofed and drained.
PreventionWaterproofing where groundwater, drainage, uplift check, water-stops at the joints.

Component materials

The network · materials
Structural conglomerate
Reinforced Concrete
Structural alloy
Steel S235 / S355
Conglomerate
Concrete

Installation processes

The network · processes
PRC.38Cast In-Situ Reinforced Concrete Frame

Reference regulations

2 norms
  • D.P.R. 380/2001Consolidated Building Act (Testo Unico Edilizia)NazionaleIn force
  • D.M. 1444/1968Mandatory limits of density, height, distance between buildings and urban standardsNazionaleIn force

Informational links to the regulatory framework. Always verify the current text on the official source.

Blueprint · Living Specification

Generate the specification item

A ready-to-edit DOCX from this system’s data — build-up, performance, and cited regulations with their current in-force status. Courtesy draft, free.